Why Did Ionity Rip Out the Fast Chargers at Its New Norway Site?
At Elverum in Norway, Ionity has removed its Ekoenergetyka pilot chargers after six EVs were immobilised while charging, and installed Huawei hardware for the first time in its network. What happened, what is on site now and what it means for drivers.

Less than a year after it opened, one of Ionity's most advanced charging sites has been stripped down and re-equipped from scratch. At Elverum, in south-eastern Norway, the network has removed the pilot chargers supplied by Polish manufacturer Ekoenergetyka following a string of incidents in which cars lost high-voltage power while plugged in. The replacement hardware comes from Huawei, the first time the carmaker-backed network has used the Chinese company's chargers. An Ionity spokesperson confirmed the switch to "electrive" on Monday, November 9.
A pilot meant to show the future
Elverum opened in December 2025 as a technology showcase. It was the only Ionity location listed at up to 500 kW and the first in the network to run Ekoenergetyka's shared-power system. Instead of each charger having its own power electronics, two power cabinets with roughly 800 kW between them split energy across six charging points in small steps, giving each car what it can accept at that moment.
In theory, that makes better use of a limited grid connection. In practice, the trial did not go to plan.
What happened to the cars
According to Norwegian and Polish reports, six incidents were logged at Elverum in which vehicles fired their pyrotechnic fuse during charging. This is a safety device in the high-voltage circuit, with a small explosive charge, that permanently cuts the battery off when the car's electronics sense danger, typically in a crash. Once it has fired, the car will not drive again until a workshop has inspected and repaired the system, which can take a long time.
"evkurier.pl" reported in October that one Volkswagen ID. Buzz owner had been waiting for a repair since late June. According to that outlet and "Elbil RADAR", insurer Zurich concluded that the damage was caused by faults in the charging equipment and would cover the repairs. Ionity had earlier told Norwegian media that the charger maker had confirmed a fault and that the units would be replaced. The exact technical cause has not been made public.
What is on site now
The station came back online in early November with entirely new hardware. Charging consultant Syed Haseeb Hassan of "eTechvolution", who first reported the change, describes a single 720 kW Huawei power unit feeding three dispensers and six charging points. Ionity's website, as cited by "electrive", lists four points at up to 600 kW and two at up to 500 kW. A separate Alpitronic unit with two 400 kW points stays in place, and the same location also hosts 28 Tesla Superchargers plus chargers from other operators.
The Ionity–Huawei tie-up was not a total surprise: the two companies announced their cooperation at the Power2Drive trade fair in Munich in summer 2026. Ionity continues to buy Ekoenergetyka's conventional all-in-one chargers of up to 350 kW, already installed in Croatia, Slovenia and Finland, and "electrive" notes that this relationship is not automatically in doubt.
What it means for drivers
Elverum is a rare case, but it shows that the car and the charger are constantly talking to each other electronically, and a fault in that exchange can strand a perfectly healthy vehicle. A few practical takeaways for long trips across Europe:
- Peak power is not everything. Headline figures of 500 or 600 kW look great, but very few cars can use them. A proven 300–400 kW charger will be just as quick for most models.
- Pilot sites are test sites. If a location is billed as a first-of-its-kind installation, plan a backup charger nearby.
- Document any serious fault. Photograph the charger screen, note the time and the charging point, and report it to the operator straight away. At Elverum, documented cases are what led the insurer to accept the equipment was at fault.
- Check the app before you arrive to confirm the site is online and see the power currently on offer.
The reassuring part is that large networks run pilots precisely so that problems like this surface at one site, not across an entire network.